Kuwait's third Al Dorra missile boat keel laid in Singapore
ST Engineering Marine laid the keel for Kuwait's third Al Dorra-class missile boat on October 20, 2026, advancing an eight-vessel programme to bolster the Kuwait Naval Force's littoral defence.

ST Engineering Marine laid the keel for Kuwait's third Al Dorra-class missile boat on October 20, 2026. The ceremony advances an eight-vessel programme for the Kuwait Naval Force, with three boats built in Singapore and five in the United Arab Emirates. The keel laying occurred three months after a plate-cutting ceremony for the same vessel in July.
ST Engineering also cut steel for the programme's fourth and fifth vessels at its Benoi Yard in Singapore on the same day. The company identified a launch window for the third vessel but did not provide launch or delivery dates for vessels four and five. The vessels are 62-metre FALAJ-3 missile boats based on ST Engineering’s Fearless-class design, tailored to Kuwait's operational requirements for littoral defence.
Programme structure and partners
The Al Dorra programme is an eight-vessel project contracted to Kuwait's Ministry of Defence. EDGE Group acts as the prime contractor, responsible for design, construction, trials, delivery, integrated logistics support, in-service support, and ammunition supply. EDGE's naval shipbuilding subsidiary, Abu Dhabi Ship Building (ADSB), was selected as the programme's build subcontractor.
ST Engineering Marine stated: "The three missile boats form part of an eight-vessel programme for the Kuwait Naval Force." The construction is split between two primary locations, with the majority of the fleet being built in the UAE.
Construction timeline and locations
The construction of the eight vessels is divided between Singapore and the United Arab Emirates. The first vessel, named AL NOUKHITHA, was launched on February 3, 2026, at ADSB’s Abu Dhabi shipyard. That launch coincided with celebrations marking ADSB’s 30th anniversary and was attended by senior officials from the UAE Navy, the Kuwait Naval Force, EDGE leadership, and programme partners.
The October 2026 keel-laying ceremony in Singapore covered construction milestones for all three Singapore-built vessels. The Kuwaiti contract followed the UAE Navy’s own acquisition of the FALAJ-3 class, with its first vessel, ALTAF, commissioned in February 2025.
Shipyard capabilities and schedule
ST Engineering Marine utilises automated panel lines, robotic profile cutters, and micro-panel fabrication at its Benoi Yard in Singapore. The ship is scheduled for launch in the third quarter of 2027.
The programme is conducted under a contract valued at AED 9 billion. The vessels are intended to be adapted to customer requirements for littoral defence operations, reinforcing Kuwait's naval posture amid regional naval modernization efforts.